Fifteen of the 29 members of the Barron County Board of Supervisors took part in a tour of the Barron County Highway Department’s old and up-and-coming new facility prior to the July 18 County Board meeting. Each month a tour is offered to orient new board members to county facilities with all welcome to attend.

Later, at the meeting, supervisors heard an update on the $25 million building project, which has run into some cost overruns. The board was informed that as of July 8, there was a budget overrun of $783,009.

Highway Department project runs into unforeseen costs

Highway Commissioner Mark Servi talks about the in-floor heat in a portion of the new highway shop during a tour of the building. The project has run into unforeseen costs.

Highway Department project runs into unforeseen costs

Garage doors were one of many supplies that have been delayed due to supply chain issues.

Highway Department project runs into unforeseen costs

Another peek inside the new highway shop with mezzanine in background.